Operations Management · PART THREE

Process and Capacity Planning

Process types and layouts, design versus effective capacity, utilization and efficiency, planning horizons, and lead or lag strategies.

Process types

Project process
One-of-a-kind output, high customization, low volume — a custom build-out.
Job shop / intermittent
Many different low-volume jobs through general-purpose equipment — a machine shop or a print shop.
Batch process
Moderate volume, moderate variety, produced in groups — a bakery.
Repetitive / assembly line
High volume, standardized output, specialized equipment.
Continuous flow
Very high volume, commodity output, running around the clock.

As volume rises and variety falls, the sensible process moves down this list, and so does unit cost. Mismatch — high variety on a line, or a job shop making a commodity — is a common and expensive error.

Layout

  • Process (functional) layout: like equipment grouped together; flexible, but longer travel and more work-in-process.
  • Product (line) layout: equipment arranged in the sequence of operations; efficient, but inflexible and vulnerable to the slowest station.
  • Cellular layout: small groups of dissimilar machines dedicated to a family of similar products.
  • Fixed-position layout: the product stays put and resources come to it — construction, shipbuilding.
  • Retail and warehouse layouts: arranged for exposure and picking efficiency rather than fabrication flow.

Capacity and its measures

Design capacity
The maximum output achievable under ideal conditions.
Effective capacity
The output achievable given the real product mix, scheduling, maintenance, breaks, and quality standards.
Actual output
What was in fact produced in the period.
Bottleneck
The resource with the least capacity in the chain; it sets the capacity of the whole process.

Formula

Utilization = Actual output ÷ Design capacityEfficiency = Actual output ÷ Effective capacityExpected output = Effective capacity × Efficiency

Worked example

Worked example: utilization and efficiency

A shop has a design capacity of 1,200 units per week and an effective capacity of 1,000 units. Last week it produced 900 units.

Formula

Utilization = 900 ÷ 1,200 = 75%Efficiency = 900 ÷ 1,000 = 90%

Efficiency is high, so the crew is running the process well. The gap between design and effective capacity — not the crew — is where the missing 300 units live.

Planning horizons

HorizonTypical spanDecisions
Long rangeOver a yearFacilities, major equipment, new locations
Intermediate range3 to 18 monthsHiring, subcontracting, tooling, inventory build
Short rangeDays to weeksScheduling, overtime, job sequencing, shift changes

Capacity strategies

Lead strategy
Add capacity before demand arrives. Protects service level and market share; risks paying for idle capacity.
Lag strategy
Add capacity only after demand is proven. Protects cash; risks stockouts, long waits, and lost customers.
Average / incremental strategy
Add capacity in small steps that track demand, alternating slight surplus and slight shortage.

Economies of scale reduce unit cost as volume grows, up to a point; beyond it, congestion, complexity, and coordination cost create diseconomies of scale.

Lean operations

Lean operations aim to deliver exactly what the customer values with the least waste. Waste is anything the customer would not pay for.

  • Overproduction — making more or sooner than needed.
  • Waiting — idle people, material, or equipment.
  • Unnecessary transportation of material.
  • Over-processing — more steps or precision than the customer requires.
  • Excess inventory hiding problems and consuming cash.
  • Unnecessary motion by workers.
  • Defects, rework, and scrap.
  • Just-in-time: material arrives as it is needed, exposing problems instead of buffering them.
  • Pull scheduling: downstream demand signals upstream production.
  • 5S and standard work: an organized, documented, repeatable workplace.
  • Continuous improvement (kaizen): small, constant, employee-driven change.

Guide: Operations Management