Printed project schedule with a bar chart, sticky notes, and a pen on a desk
Operations Management · PART TWO

Project Management

Scope, time, and cost goals; activity networks; earliest and latest times; the critical path; slack; and crashing a schedule.

What a project is

A project is a temporary set of activities with a defined beginning and end, undertaken to meet specific scope, time, and cost goals. Opening a second location, installing new equipment, and launching a product are all projects.

Scope goal
The deliverables and the work required to produce them.
Time goal
The schedule — the date the project must be complete.
Cost goal
The budget for labor, materials, and outside services.
Activity
A task that consumes time and resources.
Immediate predecessor
The activity that must finish before a given activity can start.

Building the network

  1. 1List every activity needed to complete the project.
  2. 2Identify each activity's immediate predecessors.
  3. 3Estimate the duration of each activity.
  4. 4Draw the network showing the precedence relationships.
  5. 5Compute earliest and latest times, then the critical path.
  6. 6Use the schedule to assign resources and monitor progress.
ES — earliest start
The earliest an activity can begin: the largest EF of its predecessors.
EF — earliest finish
ES + activity duration.
LF — latest finish
The latest an activity can finish without delaying the project: the smallest LS of its successors.
LS — latest start
LF − activity duration.
Slack
LS − ES (equivalently LF − EF). Slack is the amount of delay an activity can absorb without pushing the project's finish date.
Critical path
The longest path through the network. Its activities have zero slack, and its length is the project duration.

Formula

EF = ES + tLS = LF − tSlack = LS − ES = LF − EFProject duration = length of the critical path

Worked example: critical path

Worked example

Seven-activity project

Activities, predecessors, and computed times (weeks)
ActivityPredecessorDurationESEFLSLFSlack
A—303030
BA437370
CA235794
DB57127120
EC3589124
FD, E2121412140
GF4141814180

The critical path is A → B → D → F → G, and the project duration is 18 weeks. Activities C and E each carry 4 weeks of slack, so a short delay there costs nothing — a delay on the critical path delays the whole project.

CPM and PERT

CPM (Critical Path Method) assumes activity times are known with reasonable certainty. PERT (Program Evaluation and Review Technique) treats them as uncertain and uses three estimates for each activity.

Formula

Expected time t = (a + 4m + b) ÷ 6Variance v = [(b − a) ÷ 6]²where a = optimistic, m = most likely, b = pessimisticProject variance = sum of the variances of the critical-path activities

Worked example

PERT estimate

An activity is estimated at 4 weeks optimistic, 6 weeks most likely, 14 weeks pessimistic.

Formula

t = (4 + 4(6) + 14) ÷ 6 = 42 ÷ 6 = 7 weeksv = [(14 − 4) ÷ 6]² = (1.667)² = 2.78

Crashing the schedule

Crashing means paying to shorten activity durations. Two rules govern it.

  • Only crash activities on the critical path — shortening an activity with slack changes nothing.
  • Crash the critical activity with the lowest cost per period saved first, then recompute: the critical path can shift.

Formula

Crash cost per period = (Crash cost − Normal cost) ÷ (Normal time − Crash time)

Guide: Operations Management

NEXT · PART THREE: Process and Capacity Planning

Continue the guide

Need help applying this?

Baltimore resource partners offer free coaching on operations, quality, purchasing, and inventory for small businesses.